I. Preparatory Work Prior to Assembly

 

Before assembly begins, steel components must undergo material verification and surface treatment. The specifications and grades of the steel materials used must strictly align with the design documents; mixing of materials is strictly prohibited. Connection surfaces must be thoroughly cleaned to remove oil stains, mill scale, and burrs. For common components such as beams and columns, their length, curvature, and twist must be verified in advance; any components exceeding the allowable dimensional tolerances must be corrected prior to assembly.

 

II. Positioning and Layout Marking

 

Assembly operations should be conducted on a dedicated assembly platform or jig. Reference lines, centerlines, and end lines must be marked out in accordance with the construction detail drawings to ensure the accurate relative positioning of all individual parts. The assembly jig itself must possess sufficient rigidity, and the levelness of its supporting surface must be maintained within the specified tolerance range. For components such as roof trusses, end templates or positioning stops may be utilized to ensure uniform control over the precise location of the truss nodes.

 

Assembly Requirements for Steel Components

 

 

III. Assembly Sequence and Temporary Fixing

 

It is recommended to proceed with assembly in a stepwise manner, starting with the primary load-bearing components and moving toward the secondary components. The main beams and main columns should be assembled first to establish the basic structural framework, followed by the assembly of secondary beams, bracing members, and connection plates. Tack welding serves as a temporary fixing measure; the length and spacing of tack welds must meet specified requirements, and such welds must not be applied indiscriminately within critical load-bearing zones.

 

IV. Dimensional Tolerance Control

 

During the assembly process, critical dimensions-including overall length, section height, width, diagonal difference, and curvature-must be measured and monitored continuously. Appropriate compensation values ​​for weld shrinkage must be factored in and reserved either during the material cutting stage or during the assembly process. The relative positioning of bolt hole groups on connection plates intended for high-strength bolt connections must be strictly controlled, as excessive deviations in hole spacing will compromise the feasibility of field assembly.

 

V. Post-Assembly Inspection and Marking

 

Upon completion of component assembly, a comprehensive verification of both the visual appearance and the geometric dimensions of the components must be conducted. The root gaps of weld grooves, the dimensions of weld roots (lands), and the degree of misalignment at butt joints must all strictly comply with applicable standards. Upon successful inspection, the component number, gridline location, and weight information shall be marked in a conspicuous position on the component to facilitate identification during on-site hoisting.